  • Two AT-802F Fire Boss aircraft were involved in three mishaps while supporting fire suppression operations in Alaska.
  • The mishap occurred when the aircraft impacted a hill after a scoop operation, influenced by the pilot's eagerness to assist firefighters.
  • Wind conditions significantly affected the aircraft's takeoff performance, necessitating careful load management.
  • The go/no-go point is critical for ensuring safe takeoff conditions and should not be ignored even under pressure.
  • Pilots must maintain vigilance and adapt to changing conditions in austere environments to ensure safety.
Frequently asked questions
What were the main factors contributing to the mishap?

The pilot's eagerness to help firefighters and the changing wind conditions contributed to the mishap, leading to a decision to continue scooping despite increased weight and reduced takeoff distance.

What is the importance of the go/no-go point?

The go/no-go point is essential for ensuring that the aircraft has adequate flying speed and climb performance for a safe takeoff, and pilots should abort the scoop if conditions are not favorable.

How should pilots respond to changing conditions during operations?

Pilots should constantly monitor and update their performance requirements as conditions can change rapidly, and what worked in one situation may not apply in another.

What lessons were learned from the incident?

Key lessons include the need to avoid letting a sense of urgency influence decision-making, the importance of following established procedures, and the necessity of maintaining vigilance in changing conditions.

What should pilots practice to ensure safety during scoop operations?

Pilots should practice abort procedures in a controlled training environment to ensure they can effectively manage situations where the go/no-go point is not met.

Document

OAS-35A (4/18)

Interagency Aviation

Lessons Learned

No. IA LL 21-01 January 14, 2021 Page 1 of 2 Subject: Fire Boss Scooping Operations Area of Focus: Mission Focus Distribution: All Fire and Aviation Operations Discussion : Last year, two AT-802F Fire Boss aircraft were involved in three separate mishaps (two accidents and one Incident-With-Potential) while supporting fire suppression operations in Alaska. In this Lessons Learned, we will discuss one of them.

After performing a thorough reconnaissance of a river near the fire and determining that it was unsuitable for scooping, the pilots located a small lake, approximately 2000 feet long and 650 feet wide, about 4 miles north of the fire. The pilots determined that the lake was free of obstructions in the water and on the approach end of the lake. There was however, a small hill roughly 20 feet in height located at the departure (east) end. While departing with load number 12, the mishap aircraft impacted the hill with the left float. The pilot was able to continue the departure and climb to altitude where he could assess the aircraft’s condition. When the pilot began to smell fuel in the cockpit, he elected to divert and land at an airport located approximately 14 miles west of the fire.

Factors influencing the mission.

While enroute to the fire, the pilot was monitoring the air-to-ground radio frequency and heard the firefighters voicing concern about their gear being too close to the fireline. Rather than aborting the scoop that resulted in this accident, the pilot admitted to allowing his eagerness to help the firefighters influence his decision to continue with the scoop despite the increased weight and reduction in remaining takeoff distance. Although the accident occurred on the 12th scoop in the same lake, the pilot stated that he was operating under a self-imposed sense of urgency.

The winds were initially out of the east at approximately 25 miles per hour but decreased to approximately 10 miles per hour toward the end of the flight. Effectively, a headwind loss of 15 miles No. IA LL 21-01 January 14, 2021 Page 2 of 2 per hour increases the distance required to accelerate to takeoff speed, thus requiring a greater distance to clear an obstacle. The pilot stated that, “in retrospect, I should have decreased the size of the load when the wind speed started to diminish.” The reduction in the headwind had an adverse effect on the climb performance of the aircraft with the amount of water (weight) onboard which contributed to the aircraft impacting the terrain.

The “go/no-go” point is a point during the scoop at which, if not airborne, the scoop should be aborted and the load jettisoned. It is imperative to not continue scooping past the go/no go decision point if things aren’t proceeding as planned or if conditions change. The pilot stated that, “in retrospect, I should have… jettisoned the load earlier, at the go/no go point.” Lessons Learned.

1. Wanting to help is admirable - but be aware that a sense of urgency can negatively influence sound aeronautical decision making. Additionally, the loss of an airborne firefighting asset can be a serious detriment to the firefighters on the ground.

2. Procedures are in place for a reason - the go/no-go point is there to ensure aircraft possess adequate flying speed and climb performance to takeoff safely. Aborts should be practiced in a controlled training environment to ensure proficiency.

3. Maintain vigilance – conditions can always change and operating in austere environments require pilots to constantly monitor and update their performance requirements. What worked in one event may not in the next, especially if conditions have changed.

/s/ Keith C. Raley /s/ Lori Clark Keith C. Raley Lori Clark Chief, Aviation Safety, Training, Program Acting Branch Chief Aviation Safety Management Systems Evaluation, and Quality Management DOI, Office of Aviation Services USDA, Forest Service

Source & rights

Source: doi.gov. Public-domain U.S. Government work (17 USC §105) — freely reproducible.

Permanent URL — we don’t break links.

Report a problem or request removal

Document details

Doc number
Publisher
DOI Office of Aviation Services
Pages
2
File size
276 KB