This service bulletin addresses the inspection and potential replacement of the horizontal tail attachment fittings for Lake LA-4 and LA-4-200 aircraft. It outlines procedures to ensure the safety and integrity of the horizontal stabilizer attachment, following incidents of fitting failures.
- Applies to all Colonial C-2, Lake LA-4 & LA-4-200 models.
- Inspection should be completed within the next 5 hours of flight time.
- Check the gap between the fitting and the stabilizer beam.
- If the gap is less than 5/32 inches, the fitting must be removed for inspection.
- Fittings showing signs of fretting or cracks must be replaced.
- Use Alodine and primer on areas where metal is removed before reassembly.
- Follow specific steps for removal and reinstallation of the horizontal tail.
- Check the operation of the elevator and trim surfaces after reinstallation.
Document
Source
Originally published by regulations.gov. Sprinkle hosts a reference copy with an added summary, specifications and searchable full text.
Document details
- Type ·
- Service Bulletins
- Year ·
- 1998
- File size ·
- 721 KB
- Publisher ·
- regulations.gov
- Language ·
- en
What is the SERVICE BULLETIN B-78?
The SERVICE BULLETIN B-78 is a service bulletins for the LAKE LA 4/200, dated 1998.
Where does the SERVICE BULLETIN B-78 come from?
This copy of the SERVICE BULLETIN B-78 was originally published by regulations.gov and is hosted on Sprinkle as a free, searchable reference copy.
What year was the SERVICE BULLETIN B-78 published?
The SERVICE BULLETIN B-78 — the LAKE LA 4/200 service bulletins on file — is dated 1998.
Most owners only have the POH. Here's the essential set for the LAKE LA 4/200.
- Pilot's Operating Handbook / AFM
- Checklist
- Maintenance Manual
- Parts Catalog (IPC)
- Systems & Wiring
- Service Bulletins on file
- Type Certificate (TCDS)
More LAKE LA 4/200manuals & documents
Related documents
- Specifications for the Beechcraft 56TC BaronBeechcraft 56TC Baron · Specifications
- Stabilizer Fitting LC-2200-21 Maintenance Manual SupplementLAKE LA 4/200 · Maintenance Manual
- SERVICE LETTER - McFarlane AviationCESSNA 185 · Maintenance Manual
- ALERT SERVICE BULLETINBELL 407GXP · Service Bulletins
- SERVICE BULLETIN NO. 706BPiper PA-18 Super Cub · Service Bulletins
In this document
Compliance
Inspection and compliance are required within the next 5 hours of flight time.
Inspection Procedure
Inspect the fitting gap and ensure no contact with the stabilizer skin. Specific measurements and actions are outlined.
Inspection and Repair
If contact or damage is found, the fitting must be replaced. Detailed inspection methods are provided.
Appendix
Step-by-step guide for removing and reinstalling the horizontal tail halves.
Elevator and Trim Surface Checks
Specifications for elevator and trim surface travel are provided to ensure proper operation.
Safety notes
- Failure to inspect may lead to structural failure.
- Ensure proper clearance to avoid contact with the stabilizer skin.
- Use caution when removing fittings to prevent damage.
- Inspect for cracks and fretting to maintain safety.
- Follow all steps carefully to ensure correct reinstallation.
Full document text
2 April 3, 1998 DATE ISSUED SUBJECT: REVO, INC. SERVICE BULLETIN B-78 Horizontal Tail Attachment Fittings Airplanes Affected: All Colonial C-2, Lake LA-4 & LA-4-200 Models Compliance: Description: t t- + Within next 5 hours of flight time A recent incident involving failure of the attachment fitting of the left- hand horizontal stabilizer to the vertical fin has shown that a cause for initiation of a crack in the fitting can exist. The area in questions is shown below. -~---rv" -~--+- srA B"tt..l Z~K- S eA/Ill t:>OOt?Le'R ~N't:"t..i5' ~r.A3tL../Ee:.K.. 8~Nf er~A,v,Jet_ /I,, PROCEDU RE: The fitting in the area of its attachment to the horizontal stabilizer rear beam may be initially inspected by rai sing the elevator and det ermining the distance between the fitting and the flanges of the beam doubler anglel, and any contact of the fitting with the skin. (See below). Both left and right stabilizer halves, top and bottom, must be checked. The shank of a 5/32 drill bit may be used to check the gap. 1. If the gap is at least 5/32", and the stabilizer skin is not contacting the fitting, no further action is necessary. 2. If the gap is at least 5/32", but the skin has less than 1/16" clearance, simply trim off the skin edge to provide at least 1/16" clearance. 3. If the gap is less than 5/32 ", at any fitting, it will be necessary to remove the fitting in order to properly inspect it. This entails removal of the horizontal tail half from the airplane. (A guide to this procedure is in the appendix to this Bulletin.) 2 of 4 INSJ•ECTION and REPAIR: \Vith the fitting removed, inspect its forward face for evidence of actual contact with the stabilizer beam or any adjacent structure. If contact has been present, the fitting will show signs of fretting or possibly the start of a crack . Removal of paint (by light sanding) will be necessary for this inspection. Inspect the area with a magnifying glass. Dye checking, per MIL-1-68668 or equi\alent, is also recommended. If cracks, fretting, or corrosion are present, the fitting must be replaced with a new 2-2200-21 fitting. Before installing any new fitting, trim the end of the stabilizer beam doubler flange and bend radius area to provide positive clearance for the fitting. Also, use brush Alodine and primer on all areas where metal has been removed befoa·e re-assembly and re-installation of the horizontal tail. Check these before riveting the fitting in place. When installing a new fitting, center the fitting midway between the upper and lower beam and doubler flanges, with the 3/8" bolt hole 15116" (+- 1/16") inboard of the beam end. 3 of 4 APPENDIX Removal of horizontal tail halves: I. Disconnect the pushrod from the elevator horn inside the vertical tail. Allow the push rod to lower out of the way. 2. Disconnect the trim surface torque tubes near the inboard end of the horizontal tail. 3. Unbolt the elevator from the elevator horn welded assembly. 4. Remove the elevator from the stabilizer by pulling the hinge pin. 5. With the horizontal tail supported, remove the AN4 bolt from the forward beam attach point, and remove the two AN6 bolts from the rear beam attach fitting. 6. Remove the fitting from the stabilizer by carefully drilling out the AN470AD6 rivets. (Provide adequate support to the forward side of the aft beam when driving out the old rivet shanks.) 7. Repeat the procedures 2 through 6 for the other stabilizer half if necessary. 8. After installing a new or corrected fitting onto the stabilizer rear beam, reverse the above procedure for reinstallation of the horizontal tail. (Exisiting bolts and hinges may be re-used.) 9. Install all seals and access covers. (Exisiting parts may be re-used.) 10. Check travels and operation of elevator, trim surfaces, and rudder. Elevator: up 16 +-1 down 23 +-1 Trim Surfaces: up 36 deg. +2 deg. -1 deg. down 24 deg. +2 deg. -1 deg. Rudder: left 25 deg. +-I deg. right 25 deg. +-I deg. 4 of 4